Modernization at Ilim Nordic Timber
Two sawlines, six conversion stages and a tight time frame: LINCK has comprehensively modernized the infeed systems for both lines at Ilim Nordic Timber. The challenge was to implement the extensive work with as little impact as possible on ongoing sawmill operations. Through forward-looking planning and step-by-step renewal, the final conversions were completed in just three weeks each. During this period, the profiler units on Line 1 were also modernized.
Modernization from
mechanics to control
systems
Extensive modernization of existing sawmill facilities requires careful coordination between technical requirements and operational workflows. After all, the goal is to increase line's performance without interrupting ongoing sawing operations for longer than necessary. This was the task LINCK faced at Ilim Nordic Timber. The project, which began in November 2023 and was scheduled through November 2026, involved renewing the infeed systems for both sawlines. To keep production downtime at a minimum, the modernization was divided into a total of six coordinated conversion stages—three for each line.
Detailed planning and structural design of the individual stages made it possible to carry out numerous preparatory tasks while the sawmill was still in operation. This allowed the actual downtime phases to be focused exclusively on work that required the plant to be shut down. The final conversion stages took place on Line 2 in August/September 2025 and on Line 1 in August/September 2026. Only three weeks were available per line for dismantling, assembly and commissioning.
Two modernizations.
Only three weeks
of downtime.
While the focus on Line 2 was on renewing the infeed system, the final conversion of Line 1 presented an additional challenge: the profiler units were modernized in parallel with the complete reconstruction of the infeed. Both measures had to be completed within the same three-week maintenance window. To meet this deadline, precise coordination of the individual workflows was essential. At times, up to 21 LINCK employees were on-site simultaneously. The mechanical and electrical conversion work was carried out in two-shift operations with two teams each. Additionally, two teams were deployed for commissioning. Through close coordination between the departments involved, the extensive work was carried out in parallel and the available downtime was utilized effectively.
In addition to the complete reconstruction of the infeed, the work on Line 1 included essential components of the processing, control and optimization technology. As part of the modernization, four new profiler units were installed. These were supplemented by six new centering and feed units, which enable controlled transport and precise guidance of the log. The control technology was also brought up to date: the existing control system was upgraded to the TIA Portal. Furthermore, new optimization software was integrated and new peripheral modules were installed. The measures thus encompassed both the mechanical plant components and the associated control and optimization technology. Together, they form the technical foundation for the expanded capabilities in sawmill operations.
Looking to modernize your existing sawing line?
We work with you to analyze the potential of your facility and determine how targeted modernization measures can help you unlock it.
With the completion of the conversion work, both sawlines now feature high-performance infeed systems that do not require complex log turning. As a result, both lines can now be operated in mixed operation (either small or large end leading). Another advantage applies to Line 1: following the modernization, Operating Mode 3 is now available. This allows for targeted optimization of sideboards in terms of their position and width, thereby increasing the yield from the valuable raw material of wood.
For Ilim Nordic Timber, the modernization means not only an increase in the performance of the infeed systems but also additional flexibility in sawmill operations and expanded opportunities for optimizing raw material yield. The successful implementation within the tight time frame was the result of detailed preparation and the close cooperation of all parties involved.
LINCK would like to thank Ilim Nordic Timber as well as all participating employees and project partners for the trusting and successful cooperation.